October 2023

This morning, the work day went very well. The 147.090 is operating from a temporary enclosure. The existing building is unhooked all items removed, ready to leave the repeater site. Paul reported to me early this afternoon that the existing repeater building will be removed tomorrow morning. There is another work day scheduled for tomorrow morning. The new building will be installed tomorrow providing everything goes well. Helping today was:


Paul N8RLB
John KD8JSP
Bob KB8UPA
Stan W8SRD
Ed WD8JVV

Ed Ballard WD8JVV

More
  • October 9, 2023

On Wednesday there were lots of people present for the work day. A list of names will be at the end of the update. The roof of the existing building is clear (I am purposely skipping lots of details) a TV tower on the back of the building was taken down (to be used later). A lot of stuff was cleaned out of the building, not everything but a lot. The solar panel is at my house to undergo a modification.

Next work day is scheduled for Monday Oct. 9th at 9AM.
We will be switching over to the temporary repeater enclosure.
Removing everything from the old building, in preparation of installing the new building.

Present at the Wednesday work day (not in any order)

John KD8JSP
Terry W8UY
Kevin W8NI
Stan W8SRD
Paul & Kathy N8RLB
Dan N8KPQ
Ed WD8JVV

Thank all of you for the support.

Ed Ballard WD8JVV

More
  • October 5, 2023

After several days of work the latest was Friday, Saturday September 29 and 30th. In attendance were Paul N8RLB, Stan W8SRD, Ed WD8JVV, on these work days, wall studs, insulation was installed, wiring and outlets were installed. Finally wallboard was put up to cover up all internal workings. I need Stan to take a few pictures inside and outside the building, if you will please Stan. To be accomplished yet, we must remove the electrical entrance panel from the old repeater building and install it in the new building. Remove the repeaters from the existing building and relocate the 147.090 repeater in the temporary enclosure which is already installed at the site. I am leaving out lots of details that must be accomplished to complete these tasks, but you get the idea.

This is it for the update we are getting closer to being done.

Ed Ballard WD8JVV

P.S. others helping on this project were Bob Rambo, John and Barb St. Peter and I am sure more! Thank you all for supporting the effort.

More
  • October 2, 2023